- Owner: I.P.D.C
- Plant Type: Coal-fired
- Site Location: Tabas
- Capacity (MW): 650 (2*325)
- Progress: 65%
- Scope of Work: Engineering, Procurement, Construction & Commissioning of 2*35000 m3 mazut, 2*2500 m3 gasoil, 2*1000 m3 demineralized water, 1000 m3 permeate storage tanks and other sections of B.O.P Power Plant.
No comment yet, add your voice below!