• Owner: Roshd Sanat Co.
  • (Mahed Energy Co. established as the SPV Firm for Roshd Sanat)
  • Site Location: Semnan Province
  • Installation & Commissioning Period:   6 Months
  • Capacity (MW): 3.2 MW (6 small stations)
  • Progress: Completed in 2018
  • Scope of Work: Investment, Engineering, Procurement, Construction, Commissioning of the Main & B.O.P Equipment and Operation & Maintenance