Tehran Cement Factory Project

  • Owner: Tehran Cement Co.
  • Site Location: Tehran
  • Project Period: 9 months
  • Progress: Completed in 2006
  • Scope of Works: Installation and commissioning of electrical and instrumentation for replacement of unit No. 8 of

Mirza Kochak Khan Sugar Factory Project

  • Owner: Falegh Sanat Co.
  • Site Location:  Khoramshahr
  • Project Period: 12 months
  • Progress: Completed in 2004
  • Scope of Works: Installation & Commissioning of Packages 2 & 3 of sugar manufacturing facilities