Qom HEPP project (3MW) which is located in Qom water treatment plant has entered to final steps of installation & commissioning.
After completion of power plant's civil works, installation of main equipment started on early May 2017 and will finish on early July 2017, consequently pre-commissioning and trial run of Qom HEPP will be started on mid-July 2017.
Commercial operation date of Qom HEPP has been planned for mid-July 2017.
Roshd Sanat Co. as investor and EPC contractor of this project has executed all project activities within 14 months which is a good record for construction of a small hydroelectric power plant in Iran.